Weekly Roadwork Report – TxDOT Atlanta District for Nov. 22-28, 2015

Sponsor

Bowie County 

US 259 – At Red River north of De Kalb, constructing new bridge.

IH 30 – From SH 8 to Anderson Creek, repairing pavement and installing new guard rails. Various lane closures.

US 82 – From IH 30 near New Boston to DeKalb, widening highway. Various lane closures.

FM 2253 – From IH 30 to US 82 at Leary, widening highway and overpass.

US 59 – From FM 2148 in Bowie County to FM 3129 in Cass County, converting pavement to concrete on the northbound lanes.  Traffic restricted to one lane each direction in the southbound lanes.

 

Camp County

None

Cass County

US 59 – From FM 2148 in Bowie County to FM 3129 in Cass County, converting pavement to concrete on the northbound lanes.  Traffic restricted to one lane each direction in the southbound lanes.

SH 77 – From FM 251 to FM 1841 in Atlanta, widening highway.

 

Harrison County

US 59 – At Loop 390, reconstructing intersection for concrete pavement.

FM 450 – At Little Cypress Creek, replacing bridges and relocating roadway.

FM 450 – At IH 20 south of Hallsville, widening bridge and approaches.

 

Marion County

US 59 – At FM 2208, reconstructing intersection for concrete pavement. 

 

Morris County

IH 30 – From Titus County Line to Bowie County Line, repairing pavement and installing new guard rails. Various lane closures.

 

Panola County

None 

 

Titus County

IH 30 – From Franklin County Line to Morris County Line, repairing pavement and installing new guard rails. Various lane closures.

 

Upshur County

SH 155 – From south of Sabine River to US 80, replacing bridges and widening roadway.

Previous articleTexas DPS iWatch program to report possible terrorist activities