TxDOT Weekly Roadwork Report for Oct. 11-17, 2015

Sponsor

Bowie County

US 259 – At Red River north of De Kalb, constructing new bridge.
IH 30 – From SH 8 to Anderson Creek, repairing pavement and installing new guard rails. Various lane closures.
US 82 – From IH 30 near New Boston to DeKalb, widening highway. Various lane closures.
FM 991 – At Akin creek and US 67, replacing bridge, widening highway and adding lighting.
FM 2253 – From IH 30 to US 82 at Leary, widening highway and overpass.
IH 369 – at IH 30 interchange, sealing joints and decking on bridges. Various lane/ramp closures.

Camp County

None

Cass County

SH 77 – From FM 251 to FM 1841 in Atlanta, widening highway.
FM 2328 – From US 59 to SH 43, widening highway.

Harrison County

FM 450 – At Little Cypress Creek, replacing bridges and relocating roadway.
FM 450 – At IH 20 south of Hallsville, widening bridge and approaches.

Marion County

FM 726 – At Brushy Creek, replacing bridge. Highway is back open to through traffic.
US 59 – At FM 2208, reconstructing intersection for concrete pavement.

Morris County

IH 30 – From Titus County Line to Bowie County Line, repairing pavement and installing new guard rails. Various lane closures.

Panola County

Bus. 59 – From US 79 to US 59 South, resurfacing highway. Nighttime work only.

Titus County

IH 30 – From Franklin County Line to Morris County Line, repairing pavement and installing new guard rails. Various lane closures.

Upshur County

SH 155 – From south of Sabine River to US 80, replacing bridges and widening roadway.

Editor’s note: This is a schedule of work being planned for the dates noted above. Weather conditions and unforeseen problems can cause delays or cancelation of work. For more information about construction projects, contact Marcus Sandifer, Public Information Officer, TxDOT Atlanta District, 903-799-1306, marcus.sandifer@txdot.gov.

Previous articleWoman gets prison for social security theft